Estimated Project Effort

Project Effort Estimation

Component Design Development Testing Deployment Total
Shared Platform Components 4 8 4 2 18
Disease Configuration Entity 2 2 1 0.5 5.5
Dynamic Form Loading 2 4 2 1 9
Plugins & Flows (Core Logic) 2 2 1 0.5 5.5
Measles & Rubella (V2.0) 3 10 5 2 20
Form UI & Fields 1 3 2 0.5 6.5
Classification Formula 1 3 2 1 7
Repetition & Case ID Logic 1 4 1 0.5 6.5
Dengue Fever (V3.0) 2 6 3 1 12
Form UI & Fields 1 3 1.5 0.5 6
Classification & Lab Logic 1 3 1.5 0.5 6
Malaria (V4.0) 2 5 2 1 10
Form UI & Fields 1 2.5 1 0.5 5
Specific Fields & Logic 1 2.5 1 0.5 5
Meningitis (V5.0) 2 6 3 1 12
Form UI & Fields (Primary) 1 3 1.5 0.5 6
Dynamic Lab Section Logic 1 3 1.5 0.5 6
Total Estimated Effort 13 35 17 7 72

Note: This estimation is an initial guideline. Actual effort may vary based on team experience, unforeseen complexities, and changes to project scope.